Natural Gas Regulatory Board – Artifex.News https://artifexnews.net Stay Connected. Stay Informed. Sun, 30 Jun 2024 06:42:15 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.2 https://artifexnews.net/wp-content/uploads/2023/08/cropped-Artifex-Round-32x32.png Natural Gas Regulatory Board – Artifex.News https://artifexnews.net 32 32 GAIL says Urja Ganga gas pipeline completion delayed to March 2025 https://artifexnews.net/article68351403-ece/ Sun, 30 Jun 2024 06:42:15 +0000 https://artifexnews.net/article68351403-ece/ Read More “GAIL says Urja Ganga gas pipeline completion delayed to March 2025” »

]]>

GAIL, the firm executing the pipeline, said its board of directors in a meeting on June 28 approved the revision of the completion schedule.
| Photo Credit: Reuters

“The construction of the ₹12,940-crore ‘Urja Ganga’ gas pipeline, India’s most ambitious project taking environment-friendly fuel to eastern parts of the country, has been delayed by nine months and will now be completed by March 2025,” State-owned GAIL (India) Limited said.

The 3,306 km Jagdishpur-Haldia-Bokaro-Dhamra pipeline was originally targeted for completion by June 2024. But due to “delay in right of use (RoU) availability”, the completion schedule has been revised “from June 2024 to March 2025”, GAIL said in a stock exchange filing.

The bulk of the pipeline has already been constructed and gas has started to flow in most cities along the route.

Traditionally, natural gas was available for use as fuel to generate electricity, make fertilizer or turn into CNG and cooking gas only in the western and northern parts of the country, as pipelines taking the fuel from source to users were limited to these parts.

In October 2016, work on laying a pipeline from Jagdishpur in Uttar Pradesh to Haldia in West Bengal, Bokaro in Jharkhand and Dhamra in Odisha began.

The line was extended to Guwahati in Assam from Barauni in Bihar, a length of 726 km, to take the fuel to hereto-unconnected States in the eastern region.

The Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), popularly called the Pradhan Mantri Urja Ganga pipeline, is to supply gas to the eastern States of Bihar, Jharkhand, Odisha and West Bengal.

GAIL, the firm executing the pipeline, said its board of directors in a meeting on June 28 approved the revision of the completion schedule. “The completion schedule for the 240-km Dhamra-Haldia pipeline has also been revised from June 2024 to March 2025,” it added.

The company on May 10, 2019, stated that it has completed awards of all major contracts worth ₹10,500 crore for pipeline supply and laying of the integrated 3,400-km Jagdishpur-Haldia and Bokaro-Dhamra Natural Gas Pipeline (JHBDPL) and Barauni-Guwahati Pipeline (BGPL) pipeline.

The government provided 40% viability gap funding amounting to ₹5,176 crore for execution of JHBDPL. For the Barauni-Guwahati pipeline, a 60% viability gap funding, amounting to ₹5,559 crore, has been provided by the government.

The Pradhan Mantri Urja Ganga pipeline will connect all the geographical areas (more than 90) spread over Uttar Pradesh, Bihar, Orissa, West Bengal and further to the northeastern region of India.

When the project is fully completed, the northeastern/eastern part of India will become an integral part of the gas-based economy with the twin benefits of the cheapest gas transportation through Urja Ganga and gas pricing reforms.

Under the unified tariff regulations recently notified by sector regulator Petroleum and Natural Gas Regulatory Board (PNGRB), transportation tariff has been cut by about 50% to ₹99.90 per million British thermal units for the eastern parts, helping make the clean fuel more affordable.

The pipeline has already started feeding seven city gas distribution (CGD) projects in Varanasi, Patna, Ranchi, Jamshedpur, Kolkata, Bhubaneswar, and Cuttack. The pipeline also connects the refineries, located at Barauni, Haldia, and Paradip. The JHBDPL has a transmission capacity of 16 million cubic metres of natural gas a day.